We have been informed by the installers that unfinished front door replacement and repair work will continue on Thursday and Friday, October 1-2 (weather-permitting).
___
The remaining buildings (20, 22, 26, and 30) front door replacements are scheduled to begin (weather-permitting) Monday, September 21 with an expected completion date of September 24. Building 24’s front entrance will also have cosmetic work done during this time.
—--
Building 24 front door replacement is rescheduled for Monday, August 17. The schedule for the remaining buildings will follow when available.
—--
Due to unforeseen circumstances, Building 24’s door replacement on June 15 could not take place as scheduled. Please note that we will inform the community about the new installation dates for all buildings as soon as we have more information.
Thank you for your patience.
—--
Building 24 front door installation is scheduled for Monday, June 15, during construction hours of 9am-9pm. Buildings 20, 22, 26 and 30 front doors are targeted to be replaced beginning on June 22 with a TBD completion date. Residents will need to make sure to have working keys to access rear doors. Contact AMV re: procedures and fees for replacement keys, if needed. Please use ONLY the back stairwell when entering/exiting your building and going to and from the laundry room (and also remember to avoid the mailbox area) while work is taking place.